The second of two (2) Power Transformers will be delivered
Friday, August 31st to East Cookeville Substation. The first unitwas delivered in July and is expected to be put in service on Thursday, August
30th. The purchase price of $1.5 million was approved by theCookeville City Council on 10/5/2018. The units are being replaced due to
a failure of one of the existing transformers. Once installed, thenew units will provide enhanced capacity and reliability for our electric
customers. Thanks to everyone involved for their assistance.